Challenges Faced by Power Purchase Agreement
The power purchase agreements vary a lot in different states and for different kinds of energy, some of the agreements are meticulously drafted to avoid any kind of ambiguity and scope for litigation, while some are not drafted well and there is lot of scope for litigation and ambiguity...Author Name: pallavi ghorpade
The power purchase agreements vary a lot in different states and for different kinds of energy, some of the agreements are meticulously drafted to avoid any kind of ambiguity and scope for litigation, while some are not drafted well and there is lot of scope for litigation and ambiguity...
Challenges Faced By Power Purchase Agreement
India is world's 6th largest energy consumer, accounting for 3.4% of global  energy consumption. Due to India's economic rise, the demand for energy has  grown at an average of 3.6% per annum over the past 30 years. In March 2009, the  installed power generation capacity of India stood at 149,390 MW while the per  capita power consumption stood at 612 kWH1.The country's annual power production  increased from about 190 billion kWH in 1986 to more than 680 billion kWH in  20062. The Indian government has set an ambitious target to add approximately  78,000 MW of installed generation capacity by 2012. The total demand for  electricity in India is expected to cross 950,000 MW by 20303.
 
 About 75% of the electricity consumed in India is generated by thermal power  plants, 21% by hydroelectric power plants and 4% by nuclear power plants4. More  than 50% of India's commercial energy demand is met through the country's vast  coal reserves. The country has also invested heavily in recent years on  renewable sources of energy such as wind energy. As of 2008, India's installed  wind power generation capacity stood at 9,655 MW5. Additionally, India has  committed massive amount of funds for the construction of various nuclear  reactors which would generate at least 30,000 MW6. In July 2009, India unveiled  a $19 billion plan to produce 20,000 MW of solar power by 2020.
 
 Power Purchase Agreement
 A Power Purchase Agreement (PPA) is a legal contract between an electricity  generator (provider) and a power purchaser (host). The power purchaser purchases  energy, and sometimes also capacity and/or ancillary services, from the  electricity generator.
 
 The seller under the PPA is typically an independent power producer, or "IPP."  Energy sales by regulated utilities are typically highly regulated, so that no  PPA is required or appropriate. A Power Purchase Agreement (PPA) is at the heart  of any power generation project that is to be undertaken by an Independent Power  Producer (IPP). During the past decade privately owned IPPs selling electricity  to the power industry has become common place.
 
 The PPA is often regarded as the central document in the development of  independent electricity generating assets (power plants), and is a key to  obtaining project financing for the project.
 
 Emergence of power purchase agreement
 In 1992, the government amended India's Electricity Act of 1910 and opened the  electricity sector to privatization and foreign investment. An incentive package  was enacted in 1993 to provide a five year tax holiday for new projects in the  power sector and a guaranteed 16% return on foreign investment. Additionally,  the protracted project approval system was substantially revised. The IPP's were  allowed attractive terms to set up power station but they had to work with  vertically integrated SEB's and IPP's entered into power purchasing agreement  with SEB's.
 
 Although, a policy on private sector participation was announced in 1991, the  pace of private investment has been slow as most Independent Power Producers (IPPs)  were unable to achieve closure for their projects, despite progressing well on  the other clearances.
 
 De licensing of Generation
 Delays in finalization of Power Purchase Agreements (PPA) and high cost of  electricity estimated for the projects were also some of the reasons failure of  the power purchase agreement. The Electricity Bill 2000, which was introduced in  Parliament, envisaged sweeping changes to the power sector, including  delicensing generation and permitting power trading. The Bill's aim was to carry  forward reforms in the power sector without imposing any particular model on the  States. The States can choose any model which suits them. The Bill hoped to  ensure competition in power trading. The Power Trading Corporation had been set  up by the Centre to purchase power from mega projects and sell it to different  States. What was visualised at this stage was that the PTC would not be a  monopoly and power would be commodity that could be traded. The Government was  trying to include a provision to permit others to acquire licences and trade in  power.
 
 On generation too, the Bill envisaged complete delicensing of this sector,  except for some inter-State hydel projects. Power Ministry pointed out that the  Government had an ambitious target of adding 100,000 MW of capacity in the next  12 years7. This would be equal to the capacity that had been built up in the  last 53 years. This called for massive investments not only in gene ration but  also in transmission and distribution systems.
 
 There was no way the public sector could achieve this target and hence the  private sector had to be induced to participate in capacity addition in a  greater way.
 
 Electricity Act 2003, enacted on 10th June 2003, brought about a paradigm shift  by opening up the Indian power sector to competition. The act brings about  de-licensing of thermal generation, open access in transmission, open access of  distribution network in phases, multiple licensing in distribution zones and  de-licensing of rural electricity supply. This sets tone for a competitive era  in Indian power sector. This delicencing of generation opened the market of  electricity generation by private players.
 
 Legislative setup and Power Purchase Agreement
 Under the Constitution of India, electricity is a 'concurrent' subject contained  under Entry 38 List III. Hence, the Central as well as the State governments  have authority to enact legislation in regard to the power sector. The Central  Government generally provides the policy framework and the State governments  focus on specific issues. Currently, the constitution, responsibilities and  accountability of the Power sector entities in India are governed by the  following Central statutes :
 - The Electricity Act, 2003
 - The Electricity (supply) Act, 1948 (Repealed)
 - The Electricity Regulatory Commission Act, 1998 (Repealed)
 
 As per Electricity Act, 2003 following are the Sections dealing with Power  Purchase Agreement.
 
 86. Functions of State Commission
 (1) The State Commission shall discharge the following functions, namely:--
 (b) Regulate electricity purchase and procurement process of distribution  licensees including the price at which electricity shall be procured from the  generating companies or licensees or from other sources through agreements for  purchase of power for distribution and supply within the State;
 
 Section 49 of The Electricity Act, 2003 deals with agreement for the purchase  and supply of electricity.
 
 49. Agreements with respect to supply or purchase of electricity
 Where the Appropriate Commission has allowed open access to certain consumers  under section 42, such consumers, notwithstanding the provisions contained in  clause (d) of sub-section (1) of section 62, may enter into an agreement with  any person for supply or purchase of electricity on such terms and conditions  (including tariff) as may be agreed upon by them.
 
 PPA's are entered between the state electricity boards and the independent power  producers. The Electricity Act 2003 makes it mandatory for all SEBs to unbundled  into separate generation, transmission and distribution entities so as to make  them more efficient than vertically integrated utilities. However, in most  countries, vertically integrated utilities continue to remain better financial  performers and are better able to meet customer needs.
 
 The Electricity Act, 2003 completely eliminates Section 5 of Electricity  (Supply) Act, 1948, thereby abolishing the existence of SEB's as statutory  autonomous bodies, in other words the Electricity Act 2003 by totally  eliminating the Section of Electricity Supply Act, 1948, clearly converts the  SEB's into Companies under the Company Act 1956.
 
 Section 172. (Transitional provisions) :
 Notwithstanding anything to the contrary contained in this Act,-
 
 (a) a State Electricity Board constituted under the repealed laws shall be  deemed to be the State Transmission Utility and a licensee under the provisions  of this Act for a period of one year from the appointed date or such earlier  date as the State Government may notify, and shall perform the duties and  functions of the State Transmission Utility and a licensee in accordance with  the provisions of this Act and rules and regulations made there under :
 
 Provided that the State Government may, by notification, authorize the State  Electricity Board to continue to function as the State Transmission Utility or a  licensee for such further period beyond the said period of one year as may be  mutually decided by the Central Government and the State Government;
 
 The act made it mandatory for all state electricity boards (SEBs) to unbundle  into separate generation, transmission and distribution entities. As per  Electricity Act electricity act-2003 state electricity board has to be unbundled  and make it into three companies -
 
 1. Generation
 2. Distribution
 3. Transmission
 
 Power Purchase Agreement and its contents
 When the State Electricity board agrees to purchase energy form an Independent  Power Producer they enter into a Power purchase agreement. It lays down names of  the parties their rights and liabilities, the tariff to be paid and many other  things.
 
 It contains the Name of the parties, their registered office and the Date on  which the PPA is entered. A standard Power Purchase Agreement contains the  following clauses which are referred to as Articles :
 
 1. INTERPRETATION AND DEFINED TERMS
 2. SALE AND PURCHASE OF ENERGY
 3. TERM
 4. CURRENCY, PAYMENTS AND BILLING
 5. PRE-OPERATION OBLIGATIONS
 6. INTERCONNECTION
 7. METERING
 8. OPERATIONS AND MAINTENANCE
 9. MUTUAL WARRANTIES AND COVENANTS OF THE PARTIES
 10. DEFAULTS AND TERMINATION
 11. FORCE MAJEURE
 12. INDEMNIFICATION AND LIABILITY
 13. INSURANCE
 14. RESOLUTION OF DISPUTES
 15. NOTICES
 16. MISCELLANEOUS PROVISIONS
 
 Challenges faced by the Power Purchase Agreement
 Power Purchase Agreement, has gained of importance in few years but still there  are many direct and indirect challenges which affect its practicability and its  present day relevance.
 
 There are many landmark cases where there are issues relating to PPA, one of the  most landmark cases in this regard is the Enron- MSEB case8. In June of 1992,  Enron, the US energy giant engaged in negotiations with the government of India.  Enron had identified the state of Maharashtra, to negotiate a major energy  project. Negotiations were made with the state government and with the  Maharashtra State Electricity Board (MSEB). Enron's mega project proposal was  for the construction of a US$3 billion, 2015-megawatt power plant. Being the  largest project ever undertaken in India, Enron proposed that the project be  broken down into 2 phases. Initially, in phase 1 they proposed to produce 695  megawatts and would use locally produced natural gas. Phase 2 would produce  1,320 megawatts and for this they would use the natural gas imported from Qatar.  Enron chose the town Dabhol, situated on the Indian Ocean as the project site.
 
 The power project agreement entered into between the Maharashtra State  Electricity Board and the Dabhol Power Company on 8th Nov. 1993. It was set up  in two phases. Phase-I (740 mw) was initially based on naphtha but was  eventually to switch to LNG. Phase-II (1,444 mw) was based on LNG from the  outset. MSEB was required to purchase 90% of the power generated as per the  terms of the "take-or-pay" power purchase agreement (PPA) signed with the DPC.  The price was determined by a PPA detailed formula. The obligations of MSEB  under the PPA for both phases were guaranteed by the Maharashtra government. The  Centre counter-guaranteed the Maharashtra government's obligations for Phase-I.
 
 Dabhol Phase-I became operational in 1999. Construction of Phase-II was nearing  completion when a series of disputes arose between the MSEB and DPC. The plant  was shut down in June 2001, after MSEB suspended purchase of power from DPC.
 
 MSEB canceled the power purchase agreement with the Dabhol Power Company at the  time when US$300 million had already been invested and Enron and its partners  were facing a daily loss of US$250,000 each day the project was delayed.
 
 As per the terms of the original agreement, Dabhol and its partners initiated  arbitration proceeding against MSEB and the Maharashtra government. The  government in turn launched legal action to invalidate the arbitration action  alleging that illegal means had been employed to secure the contract.  Maharashtra's government officials responsible for the investigation also stated  firmly they had no wish to consider renegotiation. In the fall of 1995, Enron  managed to persuade the government of Maharashtra to reopen negotiations which  would take place in the fall. Subsequently, Chief Minister Joshi announced that  a review panel would carry out a review of the project. The review panel not  only began to discuss the restructuring with Enron executives, they also heard  the major opponents to the deal. The major issues entailed the electricity  tariff, the capital costs of the project, the payment plan and also the  environment.
 
 The original electricity the plant would produce was actually increased from the  initial proposed outage of 2,015 megawatts to 2,410 after the completion of  phase 2. Capital cost was reduced from US$2.85 billion to US$2.5 billion and the  tariff was lowered from 7.03US cents to 6.03US cents subject to the cost of fuel  and inflation.
 
 MSEB rescinded the PPA on the grounds of material misrepresentation and default  on the availability of power. MSEB had claimed rebates of over Rs 1,200 crore,  as per the PPA provisions, for DPC's failure to provide power in the stipulated  time period. These events, coupled with Enron's bankruptcy in November 2001, led  to stoppage of work at the site. As a result, an investment of nearly Rs 11,000  crore has been idle for more than four years.
 
 A writ petition was filed by the Center of Indian Trade Unions, a federation of  registered trade unions, and, Shri Abhay Mehta, a resident of Mumbai and a  citizen of India. This writ petition has been filed by way of public interest  litigation.
 
 Issues :
 Original agreement challenged after modification and revision.
 The delay was on the part of the petitioners in moving this Court to challenge  the original PPA, etc. There is no dispute about the fact that they did not  challenge it earlier. The petitioner did not bother to intervene when it was a  subject-matter of challenge before this Court in the year 1994. They were least  concerned with the PPA, guarantee and counter guarantee till the original PPA  was scrapped and a modified PPA was entered into by the Shiv Sena - BJP  Government. No explanation has been rendered for the same. The petitioners,  therefore, contend that the State of Maharashtra and the Maharashtra State  Electricity Board have acted most illegally and against public interest in  entering into a modified PPA with the very same party without even clearing them  of the grave charges of corruption, bribery, fraud and misrepresentation.
 
 Scrap original Enron Power Project Agreement on the ground of corruption and  discriminatory terms.
 
 The statement of the State Government is the foundation of the challenge of the  petitioners to the PPA and the modified PPA. The State Government had later back  tracked. The Government has gone that far to say that the filing of the suit and  the allegations made therein were not bona fide but intended to stall the  arbitration proceedings and to open a counter for renegotiation. The petitioners  also contended the guarantee and the counter-guarantee furnished by the State of  Maharashtra and the Union of India respectively. According to the petitioners,  the modified PPA has in no way improved the original PPA but in this process,  much more has been conceded by the State of Maharashtra.
 
 Grounds of challenge of PPA
 The challenge to the power project agreement ("PPA") is on various grounds. One  of the main grounds of challenge is that it was concluded without proper  clearance under the Indian Electricity (Supply) Act, 1948, in particular,  Section 29 read with Section 31 thereof. The petitioners contend that the  requisite clearance was not granted by the Central Electricity Authority ("CEA")  and if granted was not validly granted after full compliance with the  requirements of the Act. It is also contended that even if concurrence or  clearance was granted to the original PPA, there was no fresh clearance or  concurrence obtained from the CEA under Section 31 of the Act to the amended or  supple-mentary scheme. The petitioners also contend that the above PPA should be  declared as void as the same was induced by corruption, bribery, fraud and  misrepresentation.. The PPA has also been challenged on the ground of absence of  competitive bidding and lack of transparency. The contention of the petitioners  is that the such deals could not have been finalised without competitive bidding  and (iii) the PPA having been scrapped on that ground, it was not open to them  to enter into the modified PPA for a project of much bigger magnitude having far  reaching ramifications without tenders, competitive bidding and transparency and  that too on the face of charges of corruption, bribery, fraud and  misrepresentation levelled by none else but the very same Government in the suit  filed by them in this court and in their submissions before the arbitrators. The  petitioners, therefore, contend that the State of Maharashtra and the  Maharashtra State Electricity Board have acted most illegally and against public  interest in entering into a modified PPA with the very same party without even  clearing them of the grave charges of corruption, bribery, fraud and  misrepresentation.
 
 Held
 It was held that there is a long delay on the part of the petitioners in moving  this Court to challenge the original PPA, etc. There is no explanation  whatsoever, not to speak of plausible explanation, for the same. The petitioners  cannot claim that they were not aware of the PPA. There is no dispute about the  fact that they did not challenge it earlier. They even did not bother to  intervene when it was a subject-matter of challenge before this Court in the  year 199. No explanation has been rendered for the same. Entertaining such  challenge at such belated stage will cause great injustice to the contracting  parties for no fault of their own. it was clearly noted that those who purport  to work in the public interest and challenge Government action, not for personal  gain but for the benefit of the people at large, must be vigilant and watchful  and have due regard for the rights of innocent parties affected by their action.  In that view of the matter the petitioners cannot be allowed at this stage to  challenge the original PPA on the basis of the material that were available  before its scrapping and revival. The writ petition, to that extent, was held as  not maintainable on the ground of unexplained delay.
 
 It was also held that the Government cannot deny the statements or the  allegations made by it because they were made on verification in the suit filed  in this Court and before the Arbitrators in London, it wants to retract the same  on the ground that all those allegations were baseless and unfounded. The  Government has gone that far to say that the filing of the suit and the  allegations made therein were not bona fide but intended to stall the  arbitration proceedings and to open a counter for renegotiation. The petitioners  contended that much more has been conceded in favour of Enron or Dabhol than  what was given to them by the original PPA.
 
 There is no dispute about the fact that categorical allegations of corruption,  bribery, fraud and misrepresentation were made by the State Government in the  plaint in the suit filed in this Court. Equally uncontroverted is the position  that the very same allegations were reiterated by the State Government before  the Arbitrators in London and it was contended that the PPA was void on that  count. The allegations are very serious, more so when levelled by the Government  of the State, and if found correct, will have a serious effect on the PPA. The  PPA in that event may have to be held to be in conflict with the public policy  of India. Similarly, if a contract is obtained by a party by bribing the  officials of the Government or its instrumentality, very many important issues  in regard to the validity of such contract would arise. Otherwise also, even  under Section 19 of the Indian Contract Act, an agreement caused by fraud and  misrepresentation is voidable. But all those legal issues would arise only when  there is material to justify the charge. In the instant case, the petitioners do  not have with them any material as such to justify the charge of corruption,  bribery, fraud and misrepresentation. The foundation of their challenge to the  PPA and the modified PPA is the charge levelled by the State Government itself  in the plaint in the suit filed in this Court which, according to the  petitioners, amounts to admissions of the State Government under Section 17 of  the Evidence Act.
 
 In view of the foregoing discussions and for the reasons set out above, both  these Writ Petitions were dismissed. However, though the petitioners have lost  the litigation, they have succeeded in extracting from the State Government a  clear statement to the effect that what they said against Enron and did in  pursuance thereof was activated by political considerations. This case has  highlighted to the people as to how, even after 50 years of independence,  political considerations outweigh the public interest and the interest of the  State and to what extent the Government can go to justify its actions not only  before the public but even before the Courts of law.
 
 Conclusion
 During the past decade privately owned IPPs selling electricity to the power  industry has become common place. Such arrangements require some version of a  PPA. Although, a policy on private sector participation was announced in 1991,  the pace of private investment has been slow as most Independent Power Producers  (IPPs) were unable to achieve closure for their projects, despite progressing  well on the other clearances.
 
 Delays in finalization of Power Purchase Agreements (PPA) and high cost of  electricity estimated for the projects were also some of the reasons failure of  the power purchase agreement. THE Electricity Bill 2000, which was introduced in  Parliament, came in the form of Electricity Act, 2003 which delicensed the power  sector and was a major factor for the popularity of PPA.
 
 Although PPA has gained of importance in few years but still there are many  direct and indirect challenges which affect its practicability and its present  day relevance.
 
 The power purchase agreements vary a lot in different states and for different  kinds of energy, some of the agreements are meticulously drafted to avoid any  kind of ambiguity and scope for litigation, while some are not drafted well and  there is lot of scope for litigation and ambiguity.
 
 1.  http://www.livemint.com/2009/03/04222335/5-years-on-plans-fail-to-add.html
 2.  http://www.eia.doe.gov/emeu/cabs/India/Electricity.html
 3.  http://www.kwrintl.com/library/2007/indianelectricity.htm
 4.  http://www.kpmg.com/SiteCollectionDocuments/India-electricity-outlook-2008.pdf
 5.  http://www.wwindea.org/home/images/stories/worldwindenergyreport2008_s.pdf
 6.  http://business.rediff.com/report/2009/jul/22/india-commits-rupees-180k-cr-to-nuclear-trade.htm
 7.  http://www.hinduonnet.com/businessline/2000/12/01/stories/14015629.htm
 8. Center of Indian Trade Unions and another Vs. Union of India and others  AIR1997Bom79.
 The  author can be reached at: pallavighorpade@legalserviceindia.com
 The  author can be reached at: pallavighorpade@legalserviceindia.com
ISBN No: 978-81-928510-1-3
Author Bio: Pallavi Prithviraj Ghorpade II NLC email: pallavighorpade@legalserviceindia.com
Email: pallavi4482@gmail.com
Website: pallavighorpade@legalserviceindia.com
Views: 9978
How To Submit Your Article:
Follow the Procedure Below To Submit Your Articles
Submit your Article by using our online form  
  Click here
        Note* we only accept Original Articles, we will not accept 
  Articles Already Published in other websites.
  For Further Details Contact: 
  editor@legalserviceindia.com
File Your Copyright - Right Now!

Online Copyright Registration in India
Call us at: 9891244487 / or email at: admin@legalserviceindia.com
File Divorce in Delhi - Right Now!
File Your Mutual Divorce -Call us Right Now at: 9650499965 / or email at: tapsash@gmail.com
| Lawyers in India - Search By City | |||
| Delhi Chandigarh Allahabad Lucknow Noida Gurgaon Faridabad Jalandhar Vapi | Mumbai Pune Nagpur Nashik Ahmedabad Surat Indore Agra Jalgaon | Kolkata Siliguri Durgapur Janjgir Jaipur Ludhiana Dimapur Guwahati Amritsar | Chennai Chandigarh Hyderabad Coimbatore Eluru Belgaum Cochin Rajkot Jodhpur | 

