| 
                          
        Judgment: 
        (With Civil Appeal No.7561 of 2005) 
                          
        Dr. Arijit 
        Pasayat, J.: -On Challenge in these appeals is to the judgment of a
        Division Bench of the Kerala High Court holding that the order
        of cancellation dated 13.4.2005 passed by respondent No.2
        was illegal and that respondent No.1 was entitled to further
        time to furnish the bank guarantee after the order granting
        exemption in terms of Section 81(3)(b) of the Kerala Land
        Reforms Act, 1963 (in short the 'Act') is issued.
 
 The background facts in a nutshell are as follows:
 The State Government transferred 51.96 acres of land in
        favour of Goshree Island Development Authority (in short the
        'GIDA) a non statutory State Government Undertaking to
        enable it to sell it and to use the proceeds for its
        developmental schemes. GIDA was authorized to sell the land
        in public auction in part or in full. GIDA invited tenders on
        several occasions but the tenders were cancelled. Finally, as
        per Notification dated 10.1.2005 fresh tenders were invited
        and pre bid meeting was held on 10.2.2005. Tenders were
        submitted, which were opened on 16.2.2005. In the tender
        documents four options were indicated. The individual extent
        of plots mentioned in option IV which was accepted by the
        GIDA was less than the ceiling limit contemplated under
        Section 82(d) of the Act i.e. 15 acres.
 
                          
        Respondent No.1 i.e. M/s Hotel Venus International
        (hereinafter referred to as the 'Venus') was the successful
        bidder in respect of plot Nos. D3, D4 and D5 and its sister
        concerns were successful in respect of plots B, C3, C4 and C5
        under Option IV. Appellant M/s Puravankara Projects Ltd.
        was the second highest bidder in respect of plot Nos. D3, D4
        and D5 measuring about 8.78 acres each. In the pre bid
        meeting held on 10.2.2005 one of the queries raised by one of
        the participants was as to when exemption notification under
        Section 81(3)(b) of the Act would be obtained. The reply by the
        Secretary, GIDA forms the foundation of several stands in the
        present appeals. The Secretary admittedly replied as follows: 
                          
        "GIDA had moved for general exemption
        under Section 81(3)(b) of the Kerala Land
        Reforms Act from the Government and the same will be obtained in a few days".
 
                          
        On 28.2.2005 the General Council of GIDA accepted bids of
        Venus for plot Nos. D3, D4 and D5 and confirmation letters of
        the said acceptance were issued on 1.4.2005 from Cochin
        addressed to the addressees in terms of Clause 19 of the
        tender. The addressees were in Trivandrum
        (Thiruvananthapuram). 
                          
        By letter dated 31.3.2005 Venus insisted on an
        exemption notification being obtained by GIDA as a pre
        condition to fulfill the tender terms and conditions, more
        particularly relating to furnishing of bank guarantee in terms
        of Clause 10 of the tender. There is some dispute as to
        whether the bidders had received the letters because the
        postal endorsements indicate that on account of oral
        instructions of the owner of Venus, the letters were delivered
        on 28.4.2005 i.e. much after the normal period of delivery of
        letters. Appellant knowing that Venus had not furnished the
        bank guarantee in terms of Clause 10 of Tender Terms and
        Conditions vide its letter dated 19.4.2005 matched the
        highest offer in respect of the concerned plots and agreed to
        pay the entire amount in a lump sum. When GIDA did not
        respond to the offer, the appellant moved the High Court of
        Kerala by a Writ Petition (C) No.13735 of 2005 which relates to
        C.A. 7561 of 2005. Prayer in the writ petition inter alia was for
        a declaration that the tender of Venus in relation to plot Nos
        D3, D4 and D5 was to be treated as cancelled as the requisite
        bank guarantee was not furnished. A consequential prayer
        was made not to extend the time for furnishing bank
        guarantee and for a direction to GIDA to consider the
        appellant's tender which till then was not accepted. 
                          
        Learned Single Judge of the High Court passed an
        interim order restraining the alteration of the terms and
        conditions contained in the tender until further orders. In the
        meantime, Venus failed to furnish the bank guarantee and,
        therefore, GIDA issued letters of cancellation of the letters of
        confirmation issued earlier. 
                          
        The order of cancellation was challenged by Venus in
        respect of the concerned Plots in Writ Petition Nos.
        15032/2005, 15048/2005 and 15052/2005. It is to be noted
        that the first two related to plot Nos. B, C3, C4 and C5. During
        the pendency of the writ petitions, the General Council of
        GIDA in its meeting on 21.5.2005 ratified the cancellation and
        directed forfeiture of the earnest money deposited in respect of
        the bids made by Venus in respect of the plots. In the said
        meeting in respect of plot Nos. D3, D4 and D5 it was resolved
        to accept the offers made by the appellant who had offered the
        same price as that offered by Venus earlier. The decision was
        however made subject to the decision of the High Court in the
        pending writ petitions. 
                          
        The Notification of exemption of land in terms of Section
        81(3)(b) of the Act was issued and published in the official
        gazette on 20.5.2005. The learned Single Judge allowed the
        writ petition filed by Venus essentially holding that the
        exemption Notification should have preceded the tender and
        Venus could not have been expected to comply with tender
        conditions without an exemption Notification. The Writ
        Petitions filed by the appellants were dismissed. The writ
        appeals preferred in respect of the writ petitions were
        dismissed affirming the judgment of the learned Single Judge
        though on different grounds. 
                          
        It is to be noted that a Division Bench of the High Court
        had issued notice and passed interim order to maintain status
        quo in respect of the concerned plots by order dated
        18.8.2005. 
                          
        According to the appellants Venus had not come to Court
        with clean hands. Both learned Single Judge and the Division
        Bench proceeded on erroneous premises as if exemption was a
        condition precedent to issuance of tender. In fact all concerned
        knew that the exemption could be granted later on. The
        exemption was necessary only when the total area exceeded
        the prescribed limit. As noted above, the successful bidder
        could be allotted a plot of land which was less than the ceiling
        limit. It is submitted that Venus was aware that exemption notification 
        was not a condition precedent. Therefore, it had by
        its letter dated 16.3.2005 addressed to the Chief Minister of
        State expressed its willingness for execution of the sale deeds
        in respect of the plots for which they had submitted tenders.
        Prayer was made in respect of the benefit of stamp duty. In
        that context they had clearly stated in the writ petition that
        instead of waiting for instalments they had prepared to raise
        their own resources to save a huge amount. In other words,
        attempt of Venus was to save the stamp duty and absence of
        the exemption order was not even taken as a ground for
        permission to execute the sale deeds. The High Court, it is
        submitted, had erroneously considered the terms of the tender
        and the effect of Section 87 of the Act. The High Court by its
        judgment virtually re-wrote the terms of the tender document
        and in essence introduced new aspects in the contract. 
                          
        Section 87 had no application because it relates to cases
        when a person either acquires any land after the notified date
        under Section 83 of the Act by gift, purchase, mortgage with
        possession, lease, surrender or any other kind of transfer inter
        vivos or by bequest or inheritance or by otherwise. It comes
        into existence once there is acquisition of title or interest over
        the property. The agreement for sale does not create any
        interest in the property and, therefore, the High Court was not
        justified in applying Section 87 to the facts of the case. 
                          
        In response, learned counsel for Venus-respondent No.1
        submitted that Section 81(3)(b) of the Act relates to exemption.
        Section 82 specifies the ceiling area and, therefore, no person
        can hold land in excess of the ceiling limit. There is a total
        prohibition. Since the global tender notification was issued in
        respect of the entire 51 acres 96 cents of land, it was obvious
        that even if a bidder succeeds in the tender for more than 51
        acres of land he cannot own or hold the land for any purpose
        without the exemption. Clause 14 of Tender Terms and
        Conditions provides that allottees can avail loan from the
        banks/financial institutions for effecting payment and for that
        purpose GIDA was requested to issue NOC. That being so, no
        any bank or financial institution will advance any amount
        without a clear title. In the absence of the exemption
        notification legally the successful bidder cannot hold any land.
        That actually would affect the generation of finances. In the
        pre bid meeting a specific stand was raised as to when the
        exemption notification is likely to be issued and the reply of
        GIDA authorities was that it was to be obtained shortly. In the
        absence of the exemption notification the requirement of
        furnishing the bank guarantee could not have been insisted
        upon and both the learned Single Judge and the Division
        Bench have therefore rightly held that the exemption
        notification was a condition precedent. If a bidder is
        constrained to fulfill the conditions regarding payment of bank
        guarantee without exemption that would cause great hardship
        and if there is non compliance, the inevitable result would be
        that GIDA would forfeit the EMD for no fault of the tenderer.
        Therefore, the High Court has rightly accepted the contention
        of Venus that time for compliance would be computed only
        from the date of exemption notification and the receipt of the
        confirmation thereof. When the parties entered into an
        arrangement it is impliedly understood that there should be
        an effective transfer of undisputed clear title to the transferee.
        It is therefore submitted that the order of learned Single Judge
        and the Division Bench do not warrant any interference. 
                          
        A belated special leave petition has been filed by the
        State taking the stand that there has been considerable
        increase in price and cost of the land and the appellant should
        not be allowed to get the land by matching price offered by
        Venus. It is to be noted that the order of learned Single Judge
        was not challenged either by the State Government or GIDA
        and this fact has been noted by the Division Bench. 
                          
        A few clauses in the Tender Terms and Conditions need
        to be noted. They are Clauses 3, 7, 8, 10, 14 and 15 which
        read as follows:"3 The tenderers have to acquaint
        themselves with regard to the nature and other
        conditions of the land before submitting
        tender. The Tender form quoting unit rate (rate
        per cent) enclosed in sealed cover with the
        superscription "Tender for goshree Land at
        Marine Drive, Kochi" shall reach the Secretary,
        Goshree Islands Development Authority, Park
        Avenue, Kochi-682 011 before 3.00 P.M. on
        16th February, 2005. Tender received after the
        time fixed will not be considered. The tenders
        will be opened by the Secretary, GIDA or an
        officer authorized by him at 4.00 P.M. on the
        same day at District Collector's Camp office,
        Club Road, Kochi-682 011 in the presence of
        the bidders or their authorized representative
        if present.
 xx xx xx
 7. The tenders shall remain open for a
        period of 90 days.
 
                          
        8. The tenders received in each option, will
        be evaluated by the General Council and
        appropriate decision which is most
        advantageous to GIDA will be taken. The
        General Council is free to take any decision,
        which it deems fit in the best interest of GIDA.xx xx xx
 
 10. Within 10 days of receipt of confirmation
        letter, the bidder shall furnish two bank
        guarantees each covering 20% of the bid
        amount for a period of 180 days. On failure of
        compliance, the tender shall stand cancelled
        without further notice and the earnest money
        deposit shall be forfeited. If the tenderer to
        whom the notice intimating confirmation is
        sent, fails to respond within the specified time
        of 10 days, GIDA will be free to consider any
        other tender without any further notice.
 Xx xx xx
 
 14. If after payment of Ist instalment, the
        allottee desires to avail loan from
        banks/financial institutions for paying the 2nd
        and 3rd instalments of sale value of the land,
        GIDA will issue necessary NOC favouring the
        bank/financial institution.
 
 15. Sale deed will be registered and
        possession handed over to the purchaser on
        payment of the full value of the land".
 
 Sections 81(3)(b) and 87 on which much of the
        controversy revolves round read as follows:
 
 "81(3) The Government may, if they are
        satisfied that it is necessary to do so in the
        public interest.
 
 (a) xx xx xx xx
 
 (b) on account of any land being bona fide
        required for the purpose of conversion into
        plantation or for the extension or
        preservation of an existing plantation or for
        any commercial, industrial, education or
        charitable purpose, by notification in the
        Gazette, exempt such land from the
        provisions of this Chapter, subject to such
        restrictions and conditions as they deem fit
        to impose:
 
 Provided that the land referred to in
        clause (b) shall be used for the purpose for
        which it is intended within such time as the
        Government may specify in that behalf; and
        where the land is not so used within the
        time specified, the exemption shall cease to
        be in force".
 
 Section 87: Excess land obtained by gift, etc.,
        to be surrendered:-(1) Where any person
        acquires any land after the date notified under
        section 83 by gift, purchase, mortgage with
        possession lease, surrender or any other kind
        of transfer intervivos or by bequest or
        inheritance or otherwise and in consequence
        thereof the total extent of land owned or held
        by such person exceeds the ceiling area, such
        excess shall be surrendered to such authority
        as may be prescribed.
 
 Explanation I.- Where any land is exempted by
        or under section 81 and such exemption is in
        force on the date notified under section 83,
        such land shall, with effect from the date on
        which it ceases to be exempted, be deemed to
        be land acquired after the date notified under
 section 83.
 
 Explanation II.-. Where, after the date notified
        under section 83, any class of land specified in
        Schedule II has been converted into any other
        class of land specified in that Schedule or any
        land exempt under section 81 from the
        provisions of this Chapter is converted into
        any class of land not so exempt and in
        consequence thereof the total extent of land
        owned or held by a person exceeds the ceiling
        area, so much extent of land as is in excess of
        the ceiling area, shall be deemed to be land
        acquired after the said date.
 
 (1A) Any person referred to in sub-section (1)
        shall file a statement containing the
        particulars specified in sub- section (1) of
        section 85A within a period of three months of
        the date of the acquisition.
 
 (2) The provisions of sections 85 and 86 shall,
        so far as may be, apply to the vesting in the
        Government of the ownership or possession or
        both of the lands required to be surrendered
        under sub-section (1).
 
 It is clear that the Division Bench of the High Court was
        of the view that duty is cast on the Government as well as
        GIDA to inform the prospective bidders as to whether they
        propose to place any restriction or condition in granting
        exemption under Section 81(3)(b). The High Court also noted
        that both the Government and the GIDA were aware of the
        necessity of issuing a statutory notification in the gazette
        under Section 81(3)(b) of the Act failing which the entire
        contract would be rendered void and unworkable. Once the
        Government refuses exemption the entire contract would be
        frustrated, as also, the restrictions or conditions the
        Government may impose in a given case may not be
        acceptable to the parties. Disregard of statutory requirements
        may render the contract illegal and when the contract is
        entered into in violation of these statutory requirements it
        would be opposed to public policy and may violate Section 23
        of the Indian Contract Act, 1872 (in short the 'Contract Act').
        Therefore, it was held that notification under Section 81(3)(b)
        should have come before inviting the global tender so that the
        bidders were in a position to know the restrictions and
        conditions which Government would impose while granting
        exemption. That being so, learned Single Judge's view is
        affirmed by the Division Bench of the High Court.
 
 Clauses 10 and 15 in the tender document which have
        been extracted above are of considerable significance. Clause
        10 provides the mode of payment. Clause 13 provides that in
        case of non payment of 1st instalment, the bank guarantee
        can be invoked. Clause 15 provides that the sale deed is to be
        registered on payment of the full value of the land.
 
 Section 87 deals with acquisition of title after the notified
        date. Section 87(1)(a) deals with action to be taken within a
        period of three months from the date of acquisition. The bank
        guarantee was to be furnished within a period of 10 days. The
        High Court held that the contract was un- enforceable in view
        of Section 87 of the Act is not correct. The High Court mis-construed the scope of Section 87 of the Act. The reason that
        the bank guarantee was not given is of no consequence. In
        fact as rightly submitted by learned counsel for the appellant,
        Venus itself being conscious that the exemption notification
        was not necessary before furnishing of bank guarantee,
        requested for immediate registration of the sale deed. The only
        reason indicated was that if it is done before a particular date
        considerable amount of stamp duty would be saved. At that
        stage, GIDA was never even intimated by Venus that it had no
        money or that it was awaiting for bank finances or that there
        was any necessity to obtain exemption notification. It appears
        even the stands regarding the availability of finances are
        different at different points of time.
 
 In the pre bid meeting also admittedly there was no
        demand to change the condition regarding the exemption
        notification being obtained first. GIDA's stand was very
        specific. It never treated the exemption notification to be a
        condition precedent.
 
 Clause 11 also throws considerable light on the actual
        intention. The same when read with Clause 14 makes the
        position clear that if after payment of first instalment the
        allottee desires to avail loan from a bank or financial
        institution for paying the second and third instalments of the
        sale value of the land, GIDA will issue NOC in favour of
        bank/financial institution. Therefore, only after the payment
        of the first instalment, the question of GIDA issuing NOC
        arises, that too when the allottee desires to avail loan for
        paying the second and third instalments.
 
 Clause 13 provides for forfeiture in case of non payment
        of the first instalment and permits the bank guarantee to be
        invoked without further notice. It specifically provides for
        furnishing of bank guarantee in respect of the required
        percentage of the bid amount and permits cancellation of the
        tender and forfeiture of the amount deposited.
 
 The High Court also has held that the exemption
        notification can be treated as part of implied terms. It is to be
        noted that the Government itself permitted GIDA to sell the
        property initially. Section 23 of the Contract Act has really no
        application to the facts of the case. Section 87 as noted above,
        deals with acquisition after the date of notification and permits
        filing of the statement subsequently in terms of Sub-section
        (1A) of Section 87. Illegality is attached to a case where a
        person continues to hold the land and there is a requirement
        of surrender after acquisition.
 
 There is a vital distinction between the administrative
        and contractual law decisions.
 
 It is to be noted that there was no privity of contract
        between Government and the bidders. The tender conditions
        inter alia contained provisions relating to signing of contract
        and payment of money. There can be no implied terms so far
        as the Government is concerned. Terms can be claimed to be
        implied by the parties to the contract. Thus, it was open to
        the contracting parties to say that subject to obtaining
        exemption notification, the contract would be given effect to. It
        is not so in the present case.
 
 Government by a contract cannot be compelled to grant
        permission. The statutory parameters have to be kept in view.
        A condition may be there, as appears to be in present case, to
        take steps to obtain permission. An agreement may fail
        because of absence of permission. Then it becomes
        unenforceable.
 
 Certain decisions of this Court are relevant. In W.B. State
        Electricity Board v. Patel Engineering Co. Ltd. and Ors. (2001
        (2) SCC 451) it was held that the conditions cannot be
        changed. The relevant paragraphs are 24, 30 and 31. They
        read as follows:
 
 "24. The controversy in this case has arisen at
        the threshold. It cannot be disputed that this
        is an international competitive bidding which
        postulates keen competition and high
        efficiency. The bidders have or should have
        assistance of technical experts. The degree of
        care required in such a bidding is greater than
        in ordinary local bids for small works. It is
        essential to maintain the sanctity and integrity
        of process of tender/bid and also award of a
        contract. The appellant, Respondents 1 to 4
        and Respondents 10 and 11 are all bound by
        the ITB which should be complied with
        scrupulously. In a work of this nature and
        magnitude where bidders who fulfil
        prequalification alone are invited to bid,
        adherence to the instructions cannot be given
        a go-by by branding it as a pedantic approach,
        otherwise it will encourage and provide scope
        for discrimination, arbitrariness and
        favouritism which are totally opposed to the
        rule of law and our constitutional values. The
        very purpose of issuing rules/instructions is to
        ensure their enforcement lest the rule of law
        should be a casualty. Relaxation or waiver of a
        rule or condition, unless so provided under the
        ITB, by the State or its agencies (the appellant)
        in favour of one bidder would create justifiable
        doubts in the minds of other bidders, would
        impair the rule of transparency and fairness
        and provide room for manipulation to suit the
        whims of the State agencies in picking and
        choosing a bidder for awarding contracts as in
        the case of distributing bounty or charity. In
        our view such approach should always be
        avoided. Where power to relax or waive a rule
        or a condition exists under the rules, it has to
        be done strictly in compliance with the rules.
        We have, therefore, no hesitation in concluding
        that adherence to the ITB or rules is the best
        principle to be followed, which is also in the
        best public interest.
 
 30. Though clause 29 in this case appears to
        be similarly worded as in the bid documents in
        Spina case a close reading of these clauses
        shows that no power of waiver is reserved in
        the case on hand. That apart, the nature of the
        error in these two cases is entirely different.
        There, the error was apparent $ 400 for $ 4,
        non-material and waivable by the Corporation;
        in the present case the errors pointed out
        above are not simply arithmetical and clericalmistake but a deliberate mode of splitting the
        bid which would amount to rewriting the
        entries in the bid document and cannot be
        treated as non-material. Therefore, the
        judgment in Spina case does not help
        Respondents 1 to 4.
 
 31. The submissions that remains to be
        considered is that as the price bid of
        respondents 1 to 4 is lesser by 40 crores and
        80 crores than that of respondents 11 and 10
        respectively, public interest demands that the
        bid of respondents 1 to 4 should be
        considered. The Project undertaken by the
        appellant is undoubtedly for the benefit of the
        public. The mode of execution of the work of
        the Project should also ensure that the public
        interest is best served. Tenders are invited on
        the basis of competitive bidding for execution
        of the work of the Project as it serves dual
        purposes. On the one hand it offers a fair
        opportunity to all those who are interested in
        competing for the contract relating to
        execution of the work and, on the other hand it
        affords the appellant a choice to select the best
        of the competitors on a competitive price
        without prejudice to the quality of the work.
        Above all, it eliminates favouritism and
        discrimination in awarding public works to
        contractors. The contract is, therefore,
        awarded normally to the lowest tenderer which
        is in public interest. The principle of awarding
        contract to the lowest tenderer applies when
        all things are equal. It is equally in public
        interest to adhere to the rules and conditions
        subject to which bids are invited. Merely
        because a bid is the lowest the requirements of
        compliance with the rules and conditions
        cannot be ignored. It is obvious that the bid of
        respondents 1 to 4 is the lowest of bids offered.
        As the bid documents of respondents 1 to 4
        stand without correction there will be inherent
        inconsistency between the particulars given in
        the annexure and the total bid amount, it (sic
        they) cannot be directed to be considered along
        with the other bids on the sole ground of being
        the lowest."
 
 
 
 
 In Directorate of Education and Ors. v. Educomp
        Datamatics Ltd. and Ors. (2004 (4) SCC 19) it was observed as
        follows:
 "9. It is well settled now that the courts can
        scrutinise the award of the contracts by the
        Government or its agencies in exercise of their
        powers of judicial review to prevent
        arbitrariness or favouritism. However, there
        are inherent limitations in the exercise of the
        power of judicial review in such matters. The
        point as to the extent of judicial review
        permissible in contractual matters while
        inviting bids by issuing tenders has been
        examined in depth by this Court in Tata
        Cellular v. Union of India (1994 (6) SCC 651).
        After examining the entire case-law the
        following principles have been deduced: (SCC
        pp. 687-88, para 94)
 
 "94. The principles deducible from
        the above are:
 
 (1) The modern trend points to
        judicial restraint in administrative
        action.
 
 (2) The court does not sit as a court
        of appeal but merely reviews the
        manner in which the decision was
        made.
 
 (3) The court does not have the
        expertise to correct the
        administrative decision. If a review
        of the administrative decision is
        permitted it will be substituting its
        own decision, without the necessary
        expertise which itself may be fallible.
 
 (4) The terms of the invitation to
        tender cannot be open to judicial
        scrutiny because the invitation to
        tender is in the realm of contract.
        Normally speaking, the decision to
        accept the tender or award the
        contract is reached by process of
        negotiations through several tiers.
        More often than not, such decisions
        are made qualitatively by experts.
 
 (5) The Government must have
        freedom of contract. In other words,
        a fair play in the joints is a
        necessary concomitant for an
        administrative body functioning in
        an administrative sphere or quasi-
        administrative sphere. However the
        decision must not only be tested by
        the application of Wednesbury
        principle of reasonableness
        (including its other facts pointed out
        above) but must be free from
        arbitrariness not affected by bias or
        actuated by mala fides.
 
                          
        (6) Quashing decisions may impose
        heavy administrative burden on the
        administration and lead to increased
        and unbudgeted expenditure."  
                          
        10. In Air India Ltd. v. Cochin International
        Airport Ltd. (2000 (2) SCC 617), this Court
        observed: (SCC p. 623, para 7) 
                          
        "The award of a contract, whether it
        is by a private party or by a public
        body or the State, is essentially a
        commercial transaction. In arriving
        at a commercial decision
        considerations which are paramount
        are commercial considerations. The
        State can choose its own method to
        arrive at a decision. It can fix its
        own terms of invitation to tender
        and that is not open to judicial
        scrutiny. It can enter into
        negotiations before finally deciding
        to accept one of the offers made to
        it. Price need not always be the sole criterion for awarding a contract. It
        is free to grant any relaxation, for
        bona fide reasons, if the tender
        conditions permit such a relaxation.
        It may not accept the offer even
        though it happens to be the highest
        or the lowest. But the State, its
        corporations,instrumentalities and
        agencies are bound to adhere to the
        norms, standards and procedure
        laid down by them and cannot
        depart from them arbitrarily.
        Though that decision is not
        amenable to judicial review, the
        court can examine the decision-making process and interfere if it is
        found vitiated by mala fides,
        unreasonableness and
        arbitrariness." 
 
 11. This principle was again re-stated by this
        Court in Monarch Infrastructure (P) Ltd. v.
        Commr, Ulhasnagar Municipal Corpn. (2000
        (5) SCC 287) It was held that the terms and
        conditions in the tender are prescribed by the
        Government bearing in mind the nature of
        contract and in such matters the authority
        calling for the tender is the best judge to
        prescribe the terms and conditions of the
        tender. It is not for the courts to say whether
        the conditions prescribed in the tender under
        consideration were better than the ones
        prescribed in the earlier tender invitations".
 
 
 In Har Shankar and Ors. v. The Dy. Excise and Taxation
        Commr. and Ors. (1975 (1) SCC 737) the case of a bid with
        full knowledge was considered. It was observed as follows:
 
 
 "15. Learned counsel for the respondents
        raised a preliminary objection to the
        maintainability of the writ petitions filed by the
        appellants to the grant of reliefs claimed by
        them. He contends that the appellants who
        offered their bids in the auctions did so with
        knowledge of the terms and conditions
        attaching to the auctions and they cannot, by
        their writ petitions, be permitted to wriggle out
        of the contractual obligations arising out of the
        acceptance of their bids. This objection is well-founded and must be accepted.
 
 16. Those interested in running the country
        liquor vends offered their voluntarily in the
        auctions held for granting licences for the sale
        of country liquor. The terms and conditions of
        auctions were announced before the auctions
        were held and the bidders participated in the
        auction without a demur and with full
        knowledge of the commitments which the bids
        involved. The announcement of conditions
        governing the auctions were in the nature of
        an invitation to an offer to those who were
        interested in the sale of country liquor. The
        bids given in the auctions were offers made by
        prospective vendors to the Government. The
        Government's acceptance of those bids was the
        acceptance of willing offers made to it. On
        such acceptance, the contract between the
        bidders and the Government became
        concluded and a binding agreement came into
        existence between them. The successful
        bidders were then granted licences evidencing
        the terms of contract between them and the
        Government, under which they became
        entitled to sell liquor. The licensees exploited
        the respective licences for a portion of the
        period of their currency, presumably in
        expectation of a profit. Commercial
        considerations may have revealed an error of
        judgment in the initial assessment of
        profitability of the adventure but that is a
        normal incident of all trading transactions.
        Those who contract with open eyes must
        accept the burdens of the contract along with
        its benefits. The powers of Financial
        Commissioner to grant liquor licences by
        auction and to collect licence fees through the
        medium of auctions cannot by writ petitions be
        questioned by those who, had their venture
        succeeded, would have relied upon those very
        powers to found a legal claim, Reciprocal
        rights and obligations arising out of contract
        do not depend for their enforceability upon
        whether a contracting party finds it prudent to
        abide by the terms of the contract. By such a
        test no contract could ever have a binding
        force".
 
 The difference between administrative law and
        contractual law was succinctly stated in Indian Oil
        Corporation Ltd. v. Amritsar Gas Service and Ors. (1991 (1)
        SCC 533). It was noted in paras 9, 10 and 11 as follows:
 
 "9. The argument advanced by Shri Harish
        Salve on behalf of the appellant-Corporation to
        the validity of the award are these. The first
        contention is that the validity of the award has
        to be tested on the principle of private law and
        the law of contracts and not on the touchstone
        of constitutional limitations to which the
        Indian Oil Corporation Ltd., as an
        instrumentality of the State may be subject
        since the suit was based on breach of contract
        alone and the arbitrator who proceeded only
        on that basis to grant the reliefs. It is urged
        that for this reason the further questions of
        public law do not arise on the facts of the
        present case. The next contention is that the
        relief of restoration of the contract granted by
        the arbitrator is contrary to law being against
        the express prohibition in Sections 14 and 16
        of the Specific Relief Act. It is urged that the
        contract being admittedly revokable at the
        instance of either party in accordance with
        clause 28 of the agreement, the only relief
        which can be granted on the finding of breach
        of contract by the appellant-Corporation is
        damages for the notice period of 30 days and
        no more. It was then urged that the reasons
        given in the award for granting the relief of
        restoration of the distributorship are
        untenable, being contrary to law. Shri Salve contended that the 
        propositions of law indicated in the award and applied for
        granting the reliefs disclose an error of law
        apparent on the face of the award. It was also
        urged that the onus of proving valid
        termination of the contract was wrongly placed
        by the arbitrator on the appellant-Corporation
        instead of requiring the plaintiff-respondent 1
        to prove that the termination was invalid. It
        was also contended that the failure of the
        arbitrator to consider and decide the
        appellant-Corporation's counter-claim when
        the whole suit was referred for decision
        constitute legal misconduct.
 
 10. In reply, Shri Sehgal on behalf of
        respondent 1 contended that there is a
        presumption of validity of award and the
        objections not taken specifically must be
        ignored. This argument of Shri Sehgal relates
        to the grievance of the appellant relating to
        placing the onus on the appellant-Corporation
        of proving validity of the termination. This
        contention of Shri Sehgal must be upheld
        since no such specific ground is taken in theobjections of the appellant. Moreover, there
        being a clear finding by the arbitrator of
        breach of contract by invalid termination, the
        question of onus is really of no significance.
        The other arguments of Shri Sehgal are that
        the termination of distributorship casts stigma
        on the partners of the firm; counter claim of
        the appellant-Corporation was rightly not
        considered since it was not made before the
        order of the reference; the reference made
        being of all disputes in the suit, the nature of
        relief to be granted was also within the
        arbitrator's jurisdiction; and interest also must
        be awarded to the respondent.
 
 11. We may at the outset mention that it is not
        necessary in the present case to go into the
        constitutional limitations of Article 14 of the
        Constitution to which the appellant-Corporation as an instrumentality of the State
        would be subject particularly in view of the
        recent decisions of this Court in Dwarkadas
        Marfatia and Sons v. Board of Trustees of the
        Bombay, Mahabir Auto Stores v. Indian Oil
        Corporation and Shrilekha Vidyarathi v. State
        of U.P.. This is on account of the fact that the
        suit was based only on breach of contract and
        remedies flowing therefrom and it is on this
        basis alone that the arbitrator has given his
        award. Shri Salve is therefore right in
        contending that the further questions of public
        law basis on Article 14 of the Constitution do
        not arise for decision in the present case and
        the matter must be decided strictly in the
        realm of private law rights governed by the
        general law relating to contracts with reference
        to the provisions of the Specific Relief Act
        provided for non-enforceability of certain types
        of contracts. It is, therefore, in this
        background that we proceed to consider and
        decide the contentions raised before us".
 
                          
        In essence, it was held that tender terms are contractual and
        it is the privilege of the Government which invites its tenders
        and Courts did not have jurisdiction to judge as to how the
        tender terms would have to be framed.
 By observing that there was implied term which is not
        there in the tender, and postponing the time by which the
        bank guarantee has to be furnished, in essence the High
        Court directed modification of a vital term of the contract.
 
 
 In M/s New Bihar Biri Leaves Co. and Ors. v. State of
        Bihar and Ors. (1981 (1) SCC 537) it was observed at para 48
        as follows:
 
                          
        "48. It is a fundamental principle of general
        application that if a person of his own accord,
        accepts a contract on certain terms and works
        out the contract, he cannot be allowed to
        adhere to and abide by some of the terms of
        the contract which proved advantageous to
        him and repudiate the other terms of the same
        contract which might be disadvantageous to
        him. The maxim is qui approbat non reprobate
        (one who approbates cannot reprobate). This
        principle, though originally borrowed from
        Scots Law, is now firmly embodied in English
        Common Law. According to it, a party to an
        instrument or transaction cannot take
        advantage of one part of a document or
        transaction and reject the rest. That is to say,
        no party can accept and reject the same
        instrument or transaction (Per Scrutton, L.J.,
        Verschures Creameries Ltd. v. Hull @
        Netherlands Steamship Co. (1921 (2) KB 608;
        see Douglas Menzies v. Umphelby (1908 AC
        224, 232; see also Stround's Judicial
        Dictionary, Vol. I, page 169, 3rd Edn.)"
 
 In Assistant Excise Commissioner and Ors. v. Isaac
        Peter and Ors. (1994 (4) SCC 104) this Court highlighted that
        the concept of administrative law and fairness should not be
        mixed up with fair or unfair terms of the contract.
 
 It was stated in no uncertain terms that duty to act fairly
        which is sought to be imported into a contract to modify
        and/or alter its terms and/or to create an obligation upon the
        State Government which is not there in the contract is not
        covered by any doctrine of fairness or reasonableness. The
        duty to act fairly and reasonably is a doctrine developed in
        administrative law field to ensure the rule of law and to
        prevent failure of justice when the action is administrative in
 nature.
 
 Just as the principles of natural justice ensure fair
        decision where function is quasi-judicial the doctrine of
        fairness is evolved to ensure fair action when the function is
        administrative. But the said principle cannot be invoked to
        amend, alter or vary the expressed terms of the contract
        between the parties.
 
 So far as the principles relating to implied terms are
        concerned the position has been stated by Chitty on
        Contracts, 28th Edn. Chapter 13. They read as follows:
 
                          
        "A term will not however thus be implied
        unless the court is satisfied that both parties
        would, as reasonable men have agreed to it
        had it been suggested to them ..The Court
        will only imply a term if it is one which must
        necessarily have been intended by them, and
        in particular will be reluctant to make any
        implications, "where the parties have entered
        into a carefully drafted written contract
        containing detail terms agreed between
        them" A term ought not to be implied
        unless it is in all the circumstances equitable
        and reasonable . But this does not mean that a
        term will be implied merely because in all the
        circumstances it would be reasonable to do so
        or because it would improve the contract or
        make its carrying out more convenient. "the
        touchstone is always necessity and not merely
        reasonableness". "A term will not be
        implied if it would be inconsistent with the
        express wording of the contract". 
                          
        In Halsbury's Laws of England, 4th Edn, Vol. 9, the
        expression "implied terms" reads as follows:"In practice, logically implied terms and
        the other three types of implied terms tend to
        merge imperceptibly into each other, all the
        categories being justified to some extent by
        reference to the intention of the parties; and
        the distinctions between classes of implied
        terms tend to be based on convention rather
        than logic. The conventional distinction which
        will be adopted here, are as follows: (1) terms
        implied by custom; (2) terms implied by law;
        (3) other terms implied by the courts. The
        relationship between the parties may be a
        matter of profound importance in determining
        whether a contract contains a term implied
        under one of these heads.
 
 xx xx xx xx
 Implication by law- There are many cases
        where apart from local custom or usage, the
        common law has recognized a general custom that
        certain terms be incorporated into particular types
        of contract. In some of these cases, the rules having
        been decided by the courts, they have been put into
        statutory form; for example the implied terms in
        sale of goods, conveyances of interests in land, in
        contracts of marine insurance or in contractual
        licences to enter property. Frequently, such
        statutorily implied terms are expressed to give way
        to a contrary intention; but there are other cases
        where the terms implied by statute cannot be
        excluded by any contrary agreement. Yet a further
        step in the process is that where statute law has in
        a particular field codified terms implied at common
        law, the courts may import those statutory terms
        into similar transactions by way of analogy. For
        instance, the statutorily implied term as to fitness
        in a sale of goods has been imported by analogy into
        contracts for the manufacturer of dentures, repair
        of a motor car, the erection of scaffolding, the
        dyeing of a woman's hair but the courts have shown
        themselves much more reluctant to import similar
        terms as to fitness into contracts for the sale or
        lease of interests in land .The conclusion would
        appear to be that terms implied by law are not
        happily described as "implied terms": they are
        rather duties which (frequently subject to a contrary
        intention) are imposed by the law on the parties to
        particular types of contract. In deciding whether to
        create such duties, the courts tend to look, not to
        the intention of the parties, but to consideration of
        public policy ..An implied warranty, or as it
        has been called, a covenant in law, as distinguished
        from an express contract or express warranty is
        really founded on the presumed intention of the
        parties and upon reason. The implication which the
        law draws from what must obviously have been the
        intention of the parties, it draws with the object of
        giving efficacy to the transaction and preventing
        such failure of consideration as cannot have been
        within the contemplation of either side.
 
                          
        In view of what we have stated above, it is not necessary
        to deal with the grievance raised by the State Government in
        its belated Special Leave Petition. 
 Judged at from any angle the order of the learned Single
        Judge as affirmed by the Division Bench cannot be maintained
        and is set aside.
 
                          
        The appellants had stated their willingness to match the
        amount offered by Venus and also to pay interest in terms of
        the contract. It has been stated that the whole amount shall
        be paid and they shall not give any bank guarantee. Let the
        amounts offered by Venus be paid by the appellants within a
        period of one month from today with interest @12% p.a. from
        the date of allotment. The amount, if any deposited by Venus
        will be refunded with interest @ 9% from the date of deposit
        within a period of six weeks. 
                          
        The appeals are allowed but without any order as to
        costs. 
        
         Print This Judgment 
         |