| 
                          
        Judgment: 
        Arising out of SLP (C) No. 49 of 2006Dr. Arijit Pasayat, J.  
        - Leave granted
 
                          
        Controversy lies within a very 
        narrow compass.The factual background as projected by the appellant is as follows:
 On 22.12.2003 work order was issued by the respondent to the appellant. 
        There was a clause for arbitration in the agreement which was to the 
        following effect:
 
                          
        41. ARBITRATIONB&R confidently feel that there shall not arise any disputes or 
        differences during execution and completion of this order by the 
        Contractor.
 
                          
        However, in the event of any 
        disputes or differences arise between Company (B&R) and Contractor 
        (hereinafter called the said parties)  touching or concerning the 
        interpretation of the terms and conditions as performance of the order 
        or in connection therewith or the rights and liabilities of either of 
        the said parties hereto, the said parties shall endeavour to settle the 
        same amicably through mutual agreement between them, but if the mutual 
        settlement is not possible between the Company and the Contractor, the 
        provisions of the Indian Arbitration & Conciliation Act, 1996 and all 
        statutory re-enactment and modifications thereof and the rules made 
        thereunder shall apply to such arbitrations. 
                          
        4. On 27.11.2004 a notice of demand 
        was sent to the site of the respondent and it was returned with the 
        postal endorsement refused . On 30.6.2005 the request was reiterated. On 
        9.8.2005 an order was passed by the High Court on the application filed 
        by the respondent. The matter was directed to be placed before the Chief 
        Justice of the High Court for naming an arbitrator. On 19.9.2005 the 
        High Court refused to recall its order dated 9.8.2005 on the appellant s 
        petition. On 26.10.2005, this Court in SBP & Co. v. Patel Engineering 
        Ltd. & Anr. [2005 (8) SCC 618] has dealt with the nature of power 
        exercised by the Chief Justice of High Court or Chief Justice of India, 
        as the case may be, under the Arbitration and Conciliation Act, 1996 (in 
        short the Arbitration Act ) and held that same is a judicial power and 
        not an administrative power. The decision in Konkan Rly. Corpn. Ltd. v. 
        Rani Construction (P) Ltd. (2002 (2) SCC 388) was overruled in SBP & Co. 
        (supra). The conclusions per majority were as follows: 
                          
        47. We, therefore, sum up our 
        conclusions as follows:(i) The power exercised by the Chief Justice of the High Court or the 
        Chief Justice of India under Section 11(6) of the Act is not an 
        administrative power. It is a judicial power.
 
                          
        (ii) The power under Section 11(6) 
        of the Act, in its entirety, could be delegated, by the Chief Justice of 
        the High Court only to another Judge of that Court and by the Chief 
        Justice of India to another Judge of the Supreme Court. 
                          
        (iii) In case of designation of a 
        Judge of the High Court or of the Supreme Court, the power that is 
        exercised by the designated Judge would be that of the Chief Justice as 
        conferred by the statute. 
                          
        (iv) The Chief Justice or the 
        designated Judge will have the right to decide the preliminary aspects 
        as indicated in the earlier part of this judgment. These will be his own 
        jurisdiction to entertain the request, the existence of a valid 
        arbitration agreement, the existence or otherwise of a live claim, the 
        existence of the condition for the exercise of his power and on the 
        qualifications of the arbitrator or arbitrators. The Chief Justice or 
        the designated Judge would be entitled to seek the opinion of an 
        institution in the matter of nominating an arbitrator qualified in terms 
        of Section 11(8) of the Act if the need arises but the order appointing 
        the arbitrator could only be that of the Chief Justice or the designated 
        Judge. 
                          
        (v) Designation of a District Judge 
        as the authority under Section 11(6) of the Act by the Chief Justice of 
        the High Court is not warranted on the scheme of the Act. 
                          
        (vi) Once the matter reaches the 
        Arbitral Tribunal or the sole arbitrator, the High Court would not 
        interfere with the orders passed by the arbitrator or the Arbitral 
        Tribunal during the course of the arbitration proceedings and the 
        parties could approach the Court only in terms of Section 37 of the Act 
        or in terms of Section 34 of the Act. 
                          
        (vii) Since an order passed by the 
        Chief Justice of the High Court or by the designated Judge of that Court 
        is a judicial order, an appeal will lie against that order only under 
        Article 136 of the Constitution to the Supreme Court. 
                          
        (viii) There can be no appeal 
        against an order of the Chief Justice of India or a Judge of the Supreme 
        Court designated by him while entertaining an application under Section 
        11(6) of the Act. 
                          
        (ix) In a case where an Arbitral 
        Tribunal has been constituted by the parties without having recourse to 
        Section 11(6) of the Act, the Arbitral Tribunal will have the 
        jurisdiction to decide all matters as contemplated by Section 16 of the 
        Act. 
                          
        (x) Since all were guided by the 
        decision of this Court in Konkan Rly. Corpn. Ltd. v. Rani Construction 
        (P) Ltd. and orders under Section 11(6) of the Act have been made based 
        on the position adopted in that decision, we clarify that appointments 
        of arbitrators or Arbitral Tribunals thus far made, are to be treated as 
        valid, all objections being left to be decided under Section 16 of the 
        Act. As and from this date, the position as adopted in this judgment 
        will govern even pending applications under Section 11(6) of the Act. 
                          
        (xi) Where District Judges had been 
        designated by the Chief Justice of the High Court under Section 11(6) of 
        the Act, the appointment orders thus far made by them will be treated as 
        valid; but applications if any pending before them as on this date will 
        stand transferred, to be dealt with by the Chief Justice of the High 
        Court concerned or a Judge of that Court designated by the Chief 
        Justice. 
                          
        (xii) The decision in Konkan Rly. 
        Corpn. Ltd. v. Rani construction (P) Ltd. is overruled . 
                          
        5. Though arguments were advanced in 
        support of the respective stand about the legality of the impugned 
        order, it was agreed to by learned counsel for the parties that 
        following arrangement can be made. 
                          
        The appellant has nominated one Sri 
        J. Chawla to be its arbitrator. Within a period of 30 days the 
        respondent shall nominate its arbitrator. Thereafter the Chief Justice 
        of the High Court shall nominate the Presiding Arbitrator who shall be a 
        retired Judge of any High Court. 
                          
        7. Appeal is accordingly disposed of 
        with no order as to costs. 
                          
        
        
         Print This Judgment |