| 
                          
        Judgment: 
        IA No.1 in Civil Appeal No.1575 OF 2007C.K. Thakker, J
 
                          
        This petition is filed by the 
        petitioners under Section 11(6) and Section 11(12) of the Arbitration 
        and Conciliation Act, 1996 (hereinafter referred to as the Act ) read 
        with paragraph 2 of the Appointment of Arbitrators by the Chief Justice 
        of India Scheme, 1996 for appointment of Third/Presiding Arbitrator in 
        accordance with the Agreement/Contract Package No. NS-23/AP dated May 
        31, 2001 entered into between the petitioners and the respondent. 
                          
        The petitioners are a Joint Venture 
        who came together by virtue of Joint Venture Agreement dated May 10, 
        2001 for execution of certain contracts for National Highways Authority 
        of India ( NHAI for short). Petitioner No.1 is a Company registered 
        under the Laws of the Republic of Korea having its registered office at 
        75-95, Seosomoon Dong, Chung Ku, Seoul, Korea 100 110. Originally it was 
        known as YOU ONE Engineering and Construction Co. Ltd. at the time of 
        Joint Venture Agreement and also at the time of contract dated May 31, 
        2001 with NHAI. The Company has since merged with and known as Ultra 
        Construction and Engineering Co. Ltd., Seoul, Korea; i.e. in a country 
        other than India within the meaning of Section 2(f)(ii) of the Act. 
        Petitioner No.2 is a Private Limited Company incorporated and registered 
        under the Companies Act, 1956 having its registered office at A-10, 
        Panchvati, Azadpur, Delhi 110 033. 
                          
        According to the petitioners, they 
        entered into an Agreement on May 31, 2001 with the respondent for 
        execution of Contract Package No. NS-23/AP being a project for 4-Laning 
        of KM. 464.000 to KM. 474.000 of Nagpur-Hyderabad section and KM. 9.400 
        and KM. 22.300 of Hyderabad-Bangalore section of National Highway 7 in 
        the State of Andhra Pradesh at a contract price of Rs.74,88,79,544.69. 
        The Agreement contains an arbitration clause which I will refer to at an 
        appropriate stage. 
                          
        According to the petitioners, in 
        September, 2004, i.e. after more than three years of Contract-Agreement, 
        it was alleged by the respondent that the petitioners had furnished 
        forged Bank Guarantees for availing mobilization and other advances 
        under the Contract Agreement. The respondent, in view of the Arbitration 
        Clause, filed OMP No. 342 of 2004 in the High Court of Delhi against the 
        petitioners under Section 9 of the Act for interim relief. 
                          
        The High Court passed interim 
        directions restraining the petitioners from removing and/or transferring 
        machinery and stock placed by them at the site for execution of work. On 
        December 13, 2004, the respondent invoked Clause 59 of the Agreement and 
        terminated the contract. There was exchange of letters and notices 
        between the parties. Ultimately, by a communication dated April 7, 2005, 
        the petitioners intimated the respondent that in accordance with the 
        Arbitration Clause, they had appointed Hon ble Mr. Justice A.K. 
        Srivastava, a retired Judge of the High Court of Delhi as their nominee 
        Arbitrator. According to the petitioners, in the second half of June, 
        the respondent addressed a letter to Mr. C.S. Balaramamurthi, purported 
        to have been written on April 7, 2005 appointing him as the nominee 
        Arbitrator of NHAI. From the record, it appears that the two Arbitrators 
        could not agree to an appointment of Third Arbitrator. 
                          
        The respondent intended to appoint a 
        technical man as the Third Arbitrator as the matter was of a highly 
        technical nature , but the arbitrator appointed by the petitioners 
        insisted that the Presiding Arbitrator should be a retired Chief Justice 
        or a Judge of a High Court, who should be senior to him (Justice 
        Srivastava). It is also on record that the respondent appointed Mr. K.P. 
        Mohanty as the Presiding Arbitrator. Subsequently, however, his 
        appointment was not continued. In February, 2006, Justice Srivastava had 
        shown his unwillingness to continue as Arbitrator and the petitioners 
        nominated Hon ble Mr. Justice V.A. Mohta, retired Chief Justice of High 
        Court of Orissa as their nominee Arbitrator in place of Justice 
        Srivastava. Since the parties could not agree as to appointment of 
        Third/Presiding Arbitrator, the petitioners have filed the present 
        petition praying therein that the Chief Justice of India may be pleased 
        to appoint a retired Judge of the Supreme Court of India or a retired 
        Chief Justice of a High Court as Presiding Arbitrator. The Hon ble Chief 
        Justice of India designated me to deal with the matter and to pass an 
        appropriate order on the application. Accordingly the petition was 
        placed before me. 
                          
        On January 24, 2007 notice was 
        issued. Affidavits and further affidavits had been filed by the 
        parties.I have heard learned counsel on both the sides.The learned 
        counsel for the petitioners submitted that the respondent-NHAI ought to 
        have agreed to appoint a retired Judge of the Supreme Court or a retired 
        Chief Justice of a High Court as Presiding/Third Arbitrator. It was 
        submitted that when the petitioners have nominated a retired Chief 
        Justice of a High Court as their Arbitrator, the respondent ought to 
        have considered the said fact and ought to have agreed to nominate a 
        Judge, senior in rank to the Arbitrator appointed by the petitioners. It 
        was also submitted that the dispute relates to interpretation of terms 
        and conditions of the contract and there is no technical element which 
        requires appointment of a technical man. It was also stated that in 
        similar circumstances, between the same parties, a dispute had arisen 
        earlier, arbitration petitions were filed before the Chief Justice of 
        High Court of Delhi and the nominee of the Chief Justice had appointed 
        Hon ble Mr. Justice Arun Kumar, retired Judge of this Court as the 
        Presiding Arbitrator. In the instant case also, such a course ought to 
        have been adopted by the respondent. Since it was not done, the 
        petitioners are constrained to approach this Court. 
                          
        The learned counsel for the 
        respondent, on the other hand, submitted that the relevant clause 
        empowers the Council of Indian Road Congress ( IRC for short) to appoint 
        Presiding Arbitrator in case of failure of the two Arbitrators to 
        appoint Third Arbitrator. Since two Arbitrators appointed by the parties 
        (the petitioners on the one hand and the respondent on the other hand) 
        could not arrive at a consensus, it is the power of IRC to appoint a 
        Third Arbitrator and the petition is liable to be dismissed. It was also 
        submitted that a similar question came up for consideration before this 
        Court between the same parties in YOU ONE Engineering & Construction 
        Co. Ltd. & Anr. v. National Highways Authority of India, (2006) 4 
        SCC 372 and this Court has held that it is the right of IRC to appoint 
        Third Arbitrator and the petitioners could not insist for a particular 
        Arbitrator. Regarding the order passed by the Nominee of the Chief 
        Justice of High Court of Delhi, it was submitted that it was an agreed 
        order and the respondent had consented to in appointing Hon ble Mr. 
        Justice Arun Kumar, retired Judge of this Court as the Third Arbitrator. 
        The said decision, therefore, does not help the petitioner. It was also 
        urged that the question is of highly technical nature and hence IRC is 
        insisting to appoint a technical man as the Third/Presiding Arbitrator. 
        It was, therefore, prayed that the petition be dismissed. 
                          
        Having considered rival contentions 
        of the parties and having gone through the Agreement and Arbitration 
        Clause, I am of the view that the prayer of the petitioners cannot be 
        granted. It is not in dispute that the Agreement, dated May 31, 2001 
        contains an Arbitration Clause (Clause 3). The relevant part of the said 
        Clause reads thus: 
                          
        In case of dispute or difference 
        arising between the employer and a domestic contractor relating to any 
        matter arising out of or connected with this Agreement, such dispute or 
        difference shall be settled in accordance with the Arbitration and 
        Conciliation Act, 1996. The Arbitral Tribunal shall consist of 3 
        Arbitrators, one each to be appointed by the employer and the 
        contractor. The third arbitrator shall be chosen by the two arbitrators 
        so appointed by the parties and shall act as Presiding Arbitrator. In 
        case of the failure of the two arbitrators appointed by the parties to 
        reach upon a consensus within a period of 30 days from the appointment 
        of the arbitrator appointed subsequently, the Presiding Arbitrator shall 
        be appointed by the Council of Indian Road Congress .(emphasis supplied) 
                          
        A bare reading of the above clause 
        leaves no room for doubt that in case of failure of the two Arbitrators 
        appointed by the parties to reach upon a consensus, the Presiding 
        Arbitrator shall be appointed by the Council of IRC . 
                          
        It may be stated at this stage that 
        when the matter was placed before me on April 24, 2007, the parties 
        invited my attention to the aforesaid clause and it was submitted that 
        no consensus could be arrived at by the parties. Considering the fact 
        situation and the Agreement, I thought it proper that the parties should 
        undertake fresh exercise in the direction. I accordingly passed an order 
        to make one more attempt. Unfortunately, however, the effort could not 
        succeed and both the counsel stated that the matter will have to be 
        decided on merits. Accordingly, the matter was heard.In my opinion, the 
        learned counsel for the respondent is right that apart from clear 
        language of Arbitration Clause, the point is also covered by YOU ONE 
        Engineering. Almost in identical circumstances, this Court was called 
        upon to consider the provisions of the Act and the right of the 
        respondent to appoint Presiding Arbitrator under the Agreement. The 
        Court held that it is the right of IRC to appoint Presiding Arbitrator 
        in case the parties are not ad idem in appointment of Third/Presiding 
        Arbitrator. This Court stated: 
                          
        The arbitration agreement clearly 
        envisages the appointment of the presiding arbitrator by IRC. There is 
        no qualification that the arbitrator has to be a different person 
        depending on the nature of the dispute. If the parties have entered into 
        such an agreement with open eyes, it is not open to ignore it and invoke 
        exercise of powers in Section 11(6) .(emphasis supplied) 
                          
        It is, no doubt, true that the High 
        Court of Delhi has appointed Hon ble Mr. Justice Arun Kumar, retired 
        Judge of this Court as Presiding Arbitrator in OMP No. 342 of 2004 vide 
        its order dated May 22, 2006. The said order is on record of this case. 
        Three paragraphs of the said order are important and they read as under: 
                          
        3. Learned counsel for the parties 
        jointly state that whole issue can be sorted out by having a panel of 
        three arbitrators, with one arbitrator as nominated by each of the 
        parties and the presiding arbitrator to be appointed by this Court with 
        the joint consent of the learned counsel for the parties. It may be 
        noticed that as on date the petitioner has nominated Mr.L.R.Gupta, 
        Director General Works, CPWD (Retd.) while respondent has nominated 
        Justice S.B.Wad (Retd.). Justice S.B.Wad was nominated in place of 
        Justice A.K.Srivastava (Retd.), who expressed his inability to act as an 
        arbitrator. 
                          
        4. Learned counsel for the parties 
        propose that Justice Arun Kumar (Retd. Judge of the Supreme Court), 10, 
        Krishna Menon Marg, New Delhi - 110 001 (Phone : 2301-2175) be appointed 
        as the presiding arbitrator and arbitral tribunal be constituted 
        accordingly. 
                          
        5. The constitution of the presiding 
        arbitrator and arbitral tribunal as proposed by learned counsel for the 
        parties is accepted by this Court and the said tribunal shall proceed to 
        enter upon reference and determine the dispute between the parties. 
        Ordered accordingly. The constitution of the tribunal be Justice Arun 
        Kumar (Retd.) as the presiding arbitrator, Mr.L.R. Gupta and Justice S.B. 
        Wad (Retd.) as the two other members of the arbitral tribunal. The fee 
        shall be fixed by the tribunal itself .(emphasis supplied) 
                          
        The learned counsel for the 
        respondent was right when he submitted that the order was based on 
        consent of the parties. As in the present case, there is no such 
        consent, the Court has to consider the matter by interpreting an 
        Arbitration Clause. Clause 3, as observed earlier, is explicitly clear 
        and there is no ambiguity. Again, the controversy is decided by this 
        Court in YOU ONE Engineering. In my view, therefore, the petitioners 
        cannot compel the respondent to agree for a retired Judge of this Court 
        or retired Chief Justice of a High Court, senior to Hon ble Mr. Justice 
        Mohta as Presiding Arbitrator. 
                          
        It was finally submitted that even 
        if this Court is of the view that no such direction can be issued or 
        order can be passed, it may be appreciated that the petitioners have 
        chosen a retired Chief Justice of a High Court as their Arbitrator and 
        appropriate observations may be made so that IRC may appoint retired 
        Judge of this Court or a retired Chief Justice of a High Court to be the 
        Presiding Arbitrator. That would enable the petitioners to avail 
        services of an Arbitrator appointed by them. I appreciate the anxiety of 
        the petitioners. In my view, however, when the Arbitration Clause is 
        clear and the point is concluded by a decision of this Court, it would 
        not be proper on my part to make any such observation. It is, however, 
        open to the respondent to take an appropriate decision in the matter 
        keeping in view the facts in their entirety. I may only state that this 
        decision will not inhibit the respondent in taking any decision as it 
        thinks fit. 
                          
        In view of the above legal position, 
        I express no opinion on the contention of the parties as to whether the 
        controversy raised is or is not of a technical nature. Since it is not 
        necessary for me to enter into that question, I leave the matter there. 
                          
        For the foregoing reasons, the 
        application deserves to be dismissed and is accordingly dismissed, 
        however, leaving the parties to bear their own costs. 
                          
        
        
         Print This Judgment |