| 
                          
        Judgment: 
        Arising Out of S.L.P. (C) NO.14804 OF 2005 With CIVIL APPEAL NO. 1100 OF 
        2007 (Arising out of S.L.P.(c) No.12954 of 2005)
 A.K.Mathur, J. 
        - Leave granted.
 
                          
        Since the question of law involved 
        in both the appeals is common, they are disposed of by this common 
        judgment. For the sake of convenience, the facts stated in Civil Appeal 
        arising out of S.L.P.(c) No.14804 of 2005 are taken into consideration. 
                          
        This appeal is directed against the 
        order passed by learned Single Judge of the Gauhati High Court, Itanagar 
        Bench in Writ Petition No.408 of 2004 whereby learned Single Judge set 
        aside the order dated 15.9.2004 passed by the Deputy Commissioner cum 
        District Judge, Papum Pare, District, Yupia in Miscellaneous Application 
        No.10 of 2004 condoning the delay in making application under Section 34 
        of the Arbitration and Conciliation Act, 1996 (hereinafter to be 
        referred to as 'the Act' ), being not maintainable. Hence, the order 
        dated 15.9.2004 was set aside and the writ petition was allowed. 
        Aggrieved against this order passed by the High Court of Gauhati, 
        Itanagar Bench, State of Arunachal Pradesh has preferred the present 
        appeal. 
                          
        Brief facts which are necessary for 
        disposal of this appeal are that the respondent herein entered into a 
        contract agreement bearing No.DD/03 of 1992-93 with the State of 
        Arunachal Pradesh in Public Works Department for executing the 
        contractual work of construction of road bridges. The value of the work 
        in question although was initially fixed at Rs.77.43 lakhs but on the 
        basis of the post tender negotiation by and between the parties, the 
        price of the work was re-fixed at Rs.1.15 crores. The work was to be 
        completed within two calendar years from the date of commencement of the 
        work. The work commenced on 10.4.1993 and it was completed in March, 
        1999. According to the petitioner-respondent herein the delay in 
        execution of the work was due to deviation from the original scope of 
        work and several obstructions and difficulties including delay in 
        approval of the design and drawings and also in making payment against 
        running accounts bills from time to time. The respondent herein raised 
        bill for the contractual work which according to the respondent was 
        refused to be paid due to certain arbitrary and untenable reasons. Such 
        refusal gave rise to a dispute and accordingly, need arose for 
        arbitration. The respondent then approached the Court under section 
        11(6) of the Act which was numbered and registered as Arbitration Case 
        No.21 of 2000 and the same was disposed of by the High Court appointing 
        an arbitrator to adjudicate the dispute between the parties. One 
        arbitrator was appointed on 18.10.2001 but subsequently that arbitrator 
        was changed by the present arbitrator. On 12.10.2003 the arbitrator 
        passed an interim award awarding Rs.65,52,878/- with simple interest to 
        be calculated if the award amount was not paid within 60 days from the 
        date of the award. However, the period of limitation prescribed under 
        Section 34 (3) of the Act for setting aside the award expired in the 
        meantime. The appellant then wrote a letter to the arbitrator for review 
        of the award and also sought clarification in respect of the award on 
        2.4.2004. On 10.4.2004 the arbitrator by his letter stated that he had 
        no jurisdiction to entertain the request for review of the award and 
        also informed that the award dated 12.10.2003 was in fact a final award 
        pertaining to the issues involved. On 21.6.2004 the respondent- 
        petitioner filed an application for execution of the interim award dated 
        12.10.2003 before the Deputy Commissioner. On 6.8.2004 the appellant 
        filed an application under Section 34 of the Act for setting aside the 
        award dated 12.10.2003 together with an application under Section 5 of 
        the Limitation Act read with Section 34(3) of the Act for condonation of 
        delay in filing the application for setting aside the award. The said 
        application was entertained and was fixed for hearing on condonation of 
        delay after 15 days. Aggrieved against this order, a writ petition was 
        filed by the respondent herein but the same was disposed of by the High 
        Court with the observation that as the matter was pending before the 
        court below it would not be appropriate to interfere at this stage and 
        left the Deputy Commissioner to decide the matter. The Deputy 
        Commissioner, Papum Pare, Itanagar by the impugned order dated 15.9.2004 
        decided the application condoning the delay in preferring the 
        application under Section 34 of the Act by the appellant. Aggrieved 
        against this order, the present writ petition was filed by the 
        respondent herein. It is the legality of this order which was challenged 
        before the High Court. Learned Single Judge of the High Court after 
        hearing both the parties came to the conclusion that the order passed by 
        the Deputy Commissioner in condoning the delay was not correct and it 
        took the view that under section 34 of the Act, there was a delay of 
        seven months from the date of first order and a delay of six months from 
        the date of second order. 
                          
        The plea of the appellant- State 
        before the court below was that the award was passed on 12.10.2003 and a 
        copy was received on 23.10.2003. As such, the period of limitation 
        started from 23.10.2003. Since the letter was sent by the appellant to 
        the arbitrator on 2.4.20043 for review of the award and a reply thereof 
        was received on 10.4.2004 whereby the matter was clarified by the 
        arbitrator, therefore, the cause of action accrued in favour of the 
        appellant on 10.4.2004 and application under Section 34 of the Act was 
        filed on 6.8.2004 i.e. within three months and the extended period of 
        one month, therefore, it was within limitation. Though this contention 
        prevailed before the trial court but the same failed before the High 
        Court on the ground that the cause of action accrued to the appellant on 
        23.10.2003 when the appellant received the copy of the award and the 
        letter which was written on 2.4.2004 was totally misconceived. The 
        interim award was final with regard to the claims raised therein, 
        therefore, the whole exercise undertaken by the appellant was totally 
        misconceived. Hence, learned Single Judge allowed the writ petition and 
        set aside the order of the trial court. Aggrieved against this order 
        passed by the learned Single Judge, the present appeal was filed. 
                          
        We have heard learned counsel for 
        the parties and perused the record. Learned counsel for the appellant 
        tried to persuade us that in fact the cause of action has arisen to the 
        appellant on 10.4.2004 when the letter was received from the arbitrator 
        and therefore, the appellant was entitled to count the period of 
        limitation from the date of receipt of the letter from the arbitrator 
        and if the limitation was to start from 10.4.2004 then the appellant has 
        a right to move an application for setting aside of the award under 
        section 34 of the Act within three months and the extended period of one 
        month and the appellant having filed the application on 6.8.2004, 
        therefore, it was within time. The submission of learned counsel for the 
        appellant is totally misconceived and it cannot be accepted. A perusal 
        of the interim award passed by the arbitrator clearly shows that it was 
        final to the extent of the claims decided therein and it may be relevant 
        to refer to the concluding portion of the award which reads as under : 
                          
        " I further direct that the awarded 
        amount is indicated above along with the interest, wherever shown till 
        the date of interim award amounting to Rs.65,52,878.00 (Rupees Sixty 
        five lakhs fifty two thousand Eight hundred seventy eight only), shall 
        be paid by the Respondents to the Claimant within 60 days from the date 
        of the award, failing which a simple interest on the unpaid amount @ 18% 
        (Eighteen percent) per annum shall be payable to the Claimant by the 
        respondents after 60 days of this interim award." 
                          
        Therefore, this interim award which 
        did not mince any word and determined the amount after discussing the 
        claims in detail and finally calculated the amount under each of the 
        claims. Therefore, there was no confusion in this award. It was 
        absolutely thoughtlessness on the part of the appellant to have written 
        a letter after six months i.e. on 2.4.2004 seeking review of the interim 
        award to the following effect: 
                          
        " While submitting the request for 
        review the case, it is also requested that your honour may kindly 
        consider (sic.) the following points regarding mode of payments, if at 
        all, the payment is to be made, as the award given by your honour is for 
        the interim payment. 
                          
        (a) Whether payment is to be made 
        directly to M/s. Damani Construction Co. or through honourable court. 
                          
        (b) In case, the payment is to be 
        made directly to M/s.Damani Construction Co., an equivalent Bank 
        Guarantee Bond from any Nationalized Bank shall be required from the 
        Contractor since it will be an interim payment and final verdict 
        awaited. 
                          
        Submitted for your kind 
        consideration please."Firstly, the letter had been designed not strictly 
        under section 33 of the Act because under Section 33 of the Act a party 
        can seek certain correction in computation of errors, or clerical or 
        typographical errors or any other errors of a similar nature occurring 
        in the award with notice to the other party or if agreed between the 
        parties, a party may request the arbitral tribunal to give an 
        interpretation of a specific point or part of the award. This 
        application which was moved by the appellant does not come within any of 
        the criteria falling under Section 33(1) of the Act. It was designed as 
        if the appellant was seeking review of the award. Since the Tribunal had 
        no power of review on merit, therefore, the application moved by the 
        appellant was wholly misconceived. Secondly, it was prayed whether the 
        payment was to be made directly to the respondent or through the Court 
        or that the respondent might be asked to furnish Bank guarantee from a 
        nationalized Bank as it was an interim award, till final verdict was 
        awaited. Both these prayers in this case were not within the scope of 
        Section 33. Neither review was maintainable nor the prayer which had 
        been made in the application had anything to do with Section 33 of the 
        Act. The prayer was with regard to the mode of payment. When this 
        application does not come within the purview of Section 33 of the Act, 
        the application was totally misconceived and accordingly the arbitrator 
        by communication dated 10.4.2004 replied to the following effect. 
                          
        " However, for your benefit I may 
        mention here that as per the scheme of the Act of 1996, the issues/ 
        claims that have been adjudicated by the interim award dated 12.10.2003 
        are final and the same issues cannot be gone into once again at the time 
        of passing the final award." 
                          
        Therefore, the reply given by the 
        arbitrator does not give any fresh cause of action to the appellant so 
        as to move an application under Section 34 (3) of the Act. In fact, when 
        the award dated 12.10.2003 was passed the only option with the appellant 
        was either to have moved an application under Section 34 within three 
        months as required under sub-section (3) of Section 34 or within the 
        extended period of another 30 days. But in stead of that a totally 
        misconceived application was filed and there too the prayer was for 
        review and with regard to mode of payment. The question of review was 
        totally misconceived as there is no such provision in the Act for review 
        of the award by the arbitrator and the clarification sought for as to 
        the mode of payment is not contemplated under Section 33 of the Act. 
        Therefore, in this background, the application was totally misconceived 
        and the reply sent by the arbitrator does not entitle the appellant a 
        fresh cause of action so as to file an application under Section 34(3) 
        of the Act, taking it as the starting point of limitation from the date 
        of reply given by the arbitrator i.e. 10.4.2004. 
                          
        Thus, in this background, the view 
        taken by learned Single Judge appears to be justified and there is no 
        ground to interfere in this appeal. Consequently, there is no merit in 
        both the appeals and the same are dismissed with no order as to costs. 
        
         Print This Judgment |